Lord willing, this will be our final major building project at our missions base. It is a 30′ x 30′ addition that will be used for a new dining area which will also be usable for a meeting place for Bible teaching, worship and meetings.
This new floor plan (below) shows the existing bottom floor that will be completed this winter. You can see the progress of our 2026 building projects by clicking on “2026 Estimates“.

Below is a breakdown of the estimates for building materials that we need to purchase to build this building. This list may continue to grow as we develop the needs of this team.
Site Work / Excavating – $000
2″ Foam Insulation for under concrete – $2,666
Concrete & Supplies – $4,100
Radiant Heat Tubing – $420
Framing Material – $5,778
Spray Foam Insulation for Walls – $3,400
Spray Foam Insulation Above Ceiling – $5,800
Trusses – $8,700
Roofing – $7,825
Windows & Sliding Door – $4,360
Siding – $5,678
Deck – $2,140
Porch & Vaulted Ceiling Wood – $3,000
Drywall – $700
Trim – $671
Paint & Clear Polyurethane – $300
Lift & Rental Equipment – $3,000
Driveway Stone – $000
TOTAL – $58,538